Worker A can complete a job in 5 days. Worker B can complete the same job in 10 days. They work together for 2 days, then Worker A stops. How many more days does Worker B need to finish?
Answer
See all 10 steps
MathBrush is being tested with a few parent groups, and every solution on the site is open to them — one household, all children. If you were given a code, it goes in once and this device remembers it.
I have a code → See a free one like it
65 worked examples are free without a code, two from every pattern. No account, either way.
One batch repeats. Work out one batch, then multiply.
In this one. Give the job a unit count both times divide into (10), so each worker's speed becomes a whole number of units per day — and rates in the same units add.
Also uses: Same time, same distance
Items are described as a fixed group or ratio that repeats, such as tiles following a pattern, snacks sold in a fixed mix, or a rate given per hour or per item.
Children start from the grand total instead of first working out what one batch is worth. In rate questions they also confuse a duration with a clock time.
Worked examples of all 33 patterns and skills, in a booklet you can print.